BL Crew: The guys finished the exterior paint on the tippy top of the East side. All of the t&g boards have been installed on the ceiling. They look beautiful! And they have started to "wrap" the windows. Take a look at the pictures on the website.

Fam Crew: We stained and urethaned the ceiling boards, trim boards and stair pieces. The interior paint is 99% finished (with just a few corner and hard to reach places to finish in the loft area, plus the sleeping porch trim).

Summit Cabinets: The cabinets have been installed! They really make the kitchen and dining room take shape and they are beautiful (see pictures). They still have a few things to finish on the cabinets and will be doing that early next week. Travis couldn't use the old cabinet faces, however he is going to make us a hutch with those glass doors!

What's left? BL Crew will be working on the interior trim pieces, hanging doors, wainscoting in the bathrooms, the fascia, the stairs, railings, finish plumbing and electrical, and other various things. The fam will be working on finishing interior painting, cleaning up exterior paint, flooring (slate, wood floors) and bead board wall coverings as well as wainscoting.

We are SOOOO close!