Thursday, May 29, 2008

Let the building (re) begin!

Hey Fam!

My dad and I met Bob, Casey and Getty up at the cabin on Tuesday. The snow is gone and they are ready to go.

So what's going on?

1) Cory (electrician) and JC (HVAC tech) are finishing up a few loose ends next week
2) The 4-way inspection is scheduled for next Friday, June 7th. That means that once the electrician and the HVAC guy finish up a few things and we pass inspection the finishing work can begin
3) Tim (Mr. Window) is going to come take measurements for the additional windows that we want to install (triangle windows, additional windows in the upstairs bedroom (south wall) and some high windows in that same bedroom)
4) Bob and his crew will begin next week by putting the decking on the floor in the loft area
5) My dad met a cabinet guy up at the cabin last week and he will be ready to install cabinets in June sometime depending on how the other projects roll

We have given Bob and his crew a goal of August 15th. This is when Owen and Lisa want to have their rehersal dinner. They seemed to think that was a good goal and were excited to have a time frame!

Very exciting stuff!

Em